Bashemurbiprabi representative: Bangabandhu Sheikh Mujibur Rahman University of Science and Technology (Bashmurbiprabi) main gate work will be completed within this year, said the university's Vice-Chancellor Prof. Dr. AQM Mahbub 6 Meanwhile, it can be seen on the spot that the work of the main gate of the university is currently closed So far only GL work has been completed.
Talking to the students of the university in this regard, it is learned that the work of the gate was going on slowly from the beginning and at present this work is completely stopped. In this regard, the Vice Chancellor of the University said, “I have called the consulting firm at Main Gate next week. The engineer at the main gate, Ostagar, can't pay the finishing touches.
But I hope the work on the main gate will be completed within this year. "My goal is to get the main gate completed by June," he said. Meanwhile, the progress report prepared by the university shows that the RDP had allocated Rs 2.36 crore for the main gate and Kazi Mahbubur Rahman procured tenders at a cost of around Rs 2.14 crore. Subsequently, the work order was issued on 23 December 2020. According to the report, the work was to be completed by December 2021.
But the construction of the gate has progressed by 22% till December and only 4% in the next three months from July to September.
Lifestyle Desk : A well-known spice is cloves. Nakfu...
News Desk: On the occasion of the 71st birthda...
News Desk: Awami League General Secretary and ...
Economy Desk: The price of gold has been reduced in ...
Comment ( 0)